Share News Channel

For the first time in China! Two large-scale hydropower projects of the National Energy Group have a

2023-04-24 10:401600

At the end of March, the Dadu River Zhentouba II Hydropower Station and the Shaping I Hydropower Station of the National Energy Group successfully closed the cofferdams simultaneously, setting a record for the synchronous closure of two large-scale cascade hydropower projects in the same river basin in China, and made a useful exploration for the development of hydropower projects in my country.

 

  The picture shows the closure site of the Zhentoubasecondary Hydropower Station

  The Dadu River Zhentouba Class II and Shaping Class I hydropower projects are located in the Jinkouhe District of Leshan City in the lower reaches of the Dadu River. They are key construction projects in the "14th Five-Year Plan" of Sichuan Province. The total installed capacity of the Zhentouba II Hydropower Station is 300 MW, and the Shaping I Hydropower Station has a total installed capacity of 360 MW. After being put into operation, they can save more than 1 million tons of standard coal and reduce carbon dioxide emissions by more than 2 million tons each year. The two large-scale hydropower stations have achieved important node goals such as simultaneous approval, simultaneous start of construction, simultaneous first-phase cofferdam closure, and simultaneous second-phase closure.


  The picture shows the closure site of Shaping I Hydropower Station

  It is understood that this synchronous closure marks that the construction of the two projects has shifted to the construction stage of the second phase of the dam and the main work of the plant, creating conditions for the first unit to be put into operation in 2025.



Hate 0
Favorite 0
Awards 0
Comment 0
China Federation of Machinery Robot Branch investigates and visits Xianghe Robot Town
On the morning of March 9, at the invitation of Xianghe County, Song Xiaogang, Secretary-General of China Machinery Industry Federation, Executive Director and Secretary-General of Robotics Branch of

02023-04-24192

Baobian Electric held a safety production work report meeting for the first quarter
In order to tighten the responsibility of the main body of safety production, further strengthen safety performance, and promote the real implementation of safety production management, on April 6, Ba

02023-04-24190

Baobian Electric obtained the AEO advanced certification enterprise qualification from the customs
Recently, Baobian Electric obtained the AEO advanced certification enterprise qualification from the customs.After becoming a senior certified enterprise, Baobian Electric can enjoy many conveniences

02023-04-24175

Baobian Electric Hebian Company organizes employees to participate in charity blood donation activit
In order to actively promote the noble qualities of unity, friendship, and selfless dedication, pass on positive energy, and be enthusiastic about public welfare.On April 4th, Baobian Electric Hebian

02023-04-24174